Target Graph

The Target vs Actuals Graph is obtained by clicking on the Reports menu within the Projects Listing page.

(Click here to see a picture of the menu location)

 

Access Right: Project Targeting View in Web

The Project Target Graph is only available if the Project Management module is installed.

 

Purpose

The Target Graph provides a graph of actual and forecast timesheet expenditure on a project or a service. It allows the rate of expenditure to be easily visualised in a graphic format against a time line.

The graph may be produced for the whole project or an individual service.

Note that if start and finish dates are not entered for tasks, it may be impossible to create a sensible graph.

 

This topic contains

•        Instructions on how to operate the Profitability Timeline Graph

Screenshot of the Profitability Timeline Graph
An explanation of how the graph values are calculated

 

Operation

To access the Target Graph, select the Target Graph option under the Planning menu in the Project Listing page. To obtain the Project Listing page, select the Project Listing option from the top Projects menu.

The graph is available for a selected service on a project or for the project overall. This is controlled by the Service to Graph drop-down.

The Last Costed Date defines the effective date at which costs are taken from the timesheets or forecasted costs.

The Dates range of dates allows you to draw the graph for a range of dates. If left blank the graph will be drawn from the earliest expenditure/income to the latest expenditure/income.

For example, a date of 31-Jan-11 indicates that actual costs are taken from timesheets prior to 31-Jan-11 and costs after 31-Jan-11 are taken from the forecast.

If either the Service or Last Costed Date or Date Range is changed you need to click the Refresh button btnRefresh to refresh the graph.

The colours and style of the graph can be changed using the Chart Appearance and Chart Palette options above the graph.

 

Screenshot

Target_Graph

 

Calculation Logic

Graph

The graph contains three lines:

Baseline

This line shows the latest baseline targets straight line apportioned between the start and finish dates for each task. If the task has no start and finish dates the graph portion for that task will be missing.

If there is no baseline saved for any task, then the current target is used and straightlined in the same way.

Target

The target shows either:

The values from resource plans if the task is targeted using resource plane, or

Straight line apportionment between the task start and finish dates if not.

Actual Costs

The line plots the actual costs from timesheets against the timesheet dates.

 

 

Tasks Table (below the graph)

ID

Defines the planning order of the task

Task Code

Task Code

Task Name

Name of the task

Charge Method

Defines how the task is to be charged

Start Date

Target start date for the task

Finish Date

Target finish date for the task

Speculative

Defines whether the task is speculative or not:

Spec = Speculative

Conf = Confirmed

Baseline

The baseline target for the task. If the baseline is zero the latest target figure is used. The baseline is straight-lined between the task start and finish dates

Target Line

The target line is the anticipated target cost. This is not shown in the table but is drawn on the graph for comparison with the actuals.

If the target method for the task is Resource Plan, then the curve is drawn from the resource plan (including historically)

If the target method is any other the line is drawn using a straight line apportionment between the task start and finish dates.

Actual Cost

Actual costs from timesheets up to the Last Costed Date.

Cost to Complete

The cost to complete for time related costs is taken from one of:

•        Resource Plans for tasks set for resource planning

Target Schedules for tasks set for scheduled targets
Remaining Target (after deducting either the actual costs or percent complete) for all other tasks. (The choice of percent complete or actual costs is a system-wide parameter)

 

Total Cost

Actual Cost + Cost to Complete

 

Variance

Baseline – Total Cost

 

 

 

 

Any images shown may be representative of the previous version of Timemaster

Report a problem

Please report any errors on this page to timemastersupport@equisys.com