Time and Expense Costs to Date (explained)

 

Purpose

Explains how Timemaster calculates Time and Expense Costs to Date

Note NOTE: Figures from tasks marked as 'speculative' are omitted from the calculations.

 

Definition

The costs of all time, non-chargeable staff expenses, and non-outsourced project expenses that have been invoiced, or are in WIP, less any discounts (up to the reporting date)

 

How to check the figures in the software;-

Time

1.Timesheet Enquiry grid

2.Tick the Actual Time-charges option on the Include button

3.Filter by the project (if necessary)

4.Filter to only include Timesheet Line Status = ‘F’ (finalised – this will include invoiced lines too)

5.Set the high date to the reporting date

6.The total of the Resource Cost column is the cost of all the time invoiced, or currently in WIP

 

Staff Expenses (non chargeable)

1.Staff Expenses grid

2.Filter by the project (if necessary)

3.Filter to include only Expense Status = ‘A’ (approved) or ‘I’ (invoiced)

4.Set the high date to the reporting date

5.Filter the grid to only show expenses where the Charge = 0 (zero)

6.The total of the Cost column is the cost of all non-chargeable staff expenses invoiced, or currently in WIP

 

Project Expenses (non outsourced)

1.Project Expenses grid

2.Filter by the project (if necessary)

3.Filter to include only Expense Status = ‘A’ (approved) or ‘I’ (invoiced)

4.Set the high date to the reporting date

5.Filter the grid to only show expenses where the Outsourced Cost? = N

6.The total of the Cost column is the cost of all the non-outsourced project expenses invoiced, or currently in WIP

 

 

Time and Expense Costs to Date     =     Time Enquiry grid: Resource Cost     +     Staff Expenses grid: Cost     +     Project Expenses grid: Cost

 

Any images shown may be representative of the previous version of Timemaster